April 21, 2025 News
We're excited to share the progress on NEORSD's Westerly Chemically Enhanced High-Rate Treatment (CEHRT) project. To date, we've finished 20,500 cubic yards of concrete! Check out some of the recent updates on each segment of the project below.Â
💧 New High-Rate Disinfection (HRD) Tank: All concrete associated with the new HRD Tank has been completed and the installation of process equipment located in the tank has begun.
💧 Control Building: Roofing and exterior insulated metal wall panels have been completed and the process equipment installation within the building is ongoing.Â
💧 Existing Combined Storm Overflow Treatment Facility (CSOTF): Process equipment installation is wrapping up within these tanks.
Volunteering at Reid Ride
August 29, 2024Mission
2024 Builders Exchange of Dayton Awards
August 28, 2024Awards
I Build America - Ohio features Shook's Sam Tunnacliffe
August 26, 2024News
2024 One Water Ohio Conference
August 9, 2024News
Co-Op Semester in Review
August 5, 2024News
Rendering for Kent City Schools' new Career Tech Building!
July 31, 2024News
West Carrollton Schools' New Elementary School for Grades 2-4 Update!
July 30, 2024News
Sifting through pallets of paint for Matthew 25: Ministries!
July 26, 2024Mission
St. John's Medical Center 4th Floor Postpartum Ward Update
July 25, 2024News
It's time to Stuff the Bus: Donate School supplies this week!
July 24, 2024Mission
Progress Update on Mansfield WTP Project!
July 23, 2024News
Midwest Employee Appreciation Night at the Levitt Pavilion!
July 19, 2024News